top of page

Tanker Parking Apron Expansion

Project Location:

Tanker Parking Apron Expansion

output-onlinepngtools.png
output-onlinepngtools.png
output-onlinepngtools.png
output-onlinepngtools.png

Project Location:

Seymour Johnson AFB, North Carolina

Project Size:

$9.5 Million

Project Manager:

Michael Clayton

Work for this project includes:

Expand Tanker Apron by approximately 35,000 SY to provide improved apron access for current KC-135 Tanker aircraft configuration and possible future expansion to KC-46 aircraft. Construction of new pavement section including earthwork, aggregate base course, cement stabilized drainage layer, and 15" PCC pavement. Replacement of existing high mast light poles, underground water, sewer, and storm drain system, new underdrain system, relocation of existing jet blast deflectors, airfield lighting, and new airfield security fence.